top of page

Images of Fawley 

The photographs on this page illustrate some of the activities that have taken place at Fawley recently. The most recent activity has been the reconstruction of the tracks in the vicinity of the Station road crossing. 

Track Work Diary; Winter 2025/26

17th February 2026:  Finally we got some decent weather and the track from the signal box to the road crossing was tied down and checked for gauge and cant. Our Planet loco ERNIE was then used as a test load to check for any residual rail movement . 

20260217_124032_edited.jpg
20260217_143210_edited.jpg

27th January 2026: Despite the miserable weather that we have had lately, including Storm Chandra, we have been able to make considerable progress with a lot of ballast being laid on top of the new foundations and all the sleepers being put in position (approximately in the case of the line from the yard to the station). There is plenty more work to do, though.

20260127_115524cropped.jpg
IMG-20260127cropped.jpg
20251230_103250.jpg
20251230_122917.jpg

30th December 2025: Although we were supposed to have closed the site throughout the Christmas and New Year holiday, the brief emergence of (relatively|) warm and dry weather meant that we could make some significant progress on the next section. And get the project back on programme. 

20251230_150242.jpg
20251216_134544.jpg

16th December 2025: During the first week of December, we continued the excavation of the rotten sleepers as we made our way down to the road crossing next to Somersham station. It was all going so well until the rain came and we found  ourselves with a paddling pool that we didn't need! 

20251216_134524.jpg
20251118_125527.jpg

18th November: Making good use of the late autumn weather, an excellent start is made on the first section of track.  Firstly, the concrete top layer had to be broken out and the timber sleepers underneath exposed.  These were found to be in very poor condition, it being 60 years since they were installed. The rotten timbers were hauled out and concrete replacements on ballast were installed in their place.  A new concrete top layer will be laid in place after all the heavy replacement work is complete. Without the help of Site Manager  Roy Twigger and his array of 'Tonka Toys', the whole exercise would have been impossible for us to undertake.

2nd December 2025: With the sleepers in place for the first track panel, it was time to refix the rails, ensuring that the height, gauge and cant were all within acceptable limits. At this stage, we were still enjoying some beautiful, mild and sunny weather.

By the end of the day, the panel had been ballasted  and the area left (relatively) neat and tidy for the annual Fawley Hill Nativity Festival.

Work4 Dec 2025 edited.jpg

0-6-0ST 'No 31' climbs the hill

O gaugeCG.jpg
No 31 at footbridge.jpg

Almost there! No 31 reaches the top of the hill

One of our resident 0 gauge layouts, William Street on display.  A Class 47 rubs shoulders with a Castle class loco. 

Meercat edited.jpg
Loony peacoc edited.jpg
Somersham at night.jpg

Somersham Station at night

Lady Judy edited.jpg

Judy, Lady McAlpine, addresses members on Barbecue Day, September 2022

Railway Shop small.jpg

Browsing at the shop

CaravanRC edited.jpg

A newly-restored caravan recently added to the Museum site

Coming up the hill small.jpg

Coming up the hill

Deer edited.jpg
Model 1 small.jpg

One of several model layouts on display - the bushes are real!

deer2 edited.jpg
bottom of page